Austin Storms runs Bitcoin mining at Galaxy Digital, a firm better known for trading and asset management. On day two of Mining Disrupt Miami 2024, held June 24–26, 2024, he sat down with Taras Kulyk to explain how a troubled mine near Lubbock, Texas, became the firm's flagship infrastructure asset, and why he will not promise that it stays a Bitcoin mine.

From a karate school to West Texas

Storms said he came into the industry in late 2016, when a family friend wanted to mine Bitcoin and the two of them put a 500 kilowatt facility behind his father's karate school outside New Orleans. He went on to start a company called Bearbox, where he worked on early demand response programs in ERCOT, the Southwest Power Pool and MISO, and then worked with the team at Great American Mining.

I left Great American Mining at the end of 2021 and joined Galaxy Digital to lead up all of our proprietary mining operations.

Austin Storms · 1:33

Galaxy, he reminded the room, is a diversified financial services firm with three business lines: global markets, asset management and digital infrastructure solutions. Mining sits in the third, next to staking and validation. Plenty of people, he said, have no idea the firm mines at all.

Buying Helios

At the end of 2022 Galaxy bought the Helios site from Argo. Storms described the price as a discount to what the firm now believes the campus is worth. When his team took over, he said, the facility was drawing roughly 60 to 65 megawatts, about 60 to 70% of the build was finished, and there was a long list of operational and engineering problems to fix. He gave Argo's team credit for getting that far on a compressed schedule.

After the repairs the site draws between 180 and 200 megawatts, with the exact figure moving with the Texas heat.

Today it sits as, I believe, and nobody's corrected me yet, the largest single loop, single phase immersion build in the entire world.

Austin Storms · 3:17

Almost 150 megawatts of that load runs inside the 126,000 square foot main building, shared between Galaxy's own machines and two large hosting clients.

Why the expansion was air-cooled

Kulyk asked why a team with an immersion hall of that size chose something else for its next phase. Cost, Storms answered. Quotes for more immersion capacity came back at 400, 500 and 600 thousand dollars a megawatt, and close to 800 once everything was included.

So he phoned RK Mission Critical and asked whether it had spare containers. It did, and they were already in Texas. Galaxy paid less than list price, because the bear market had left no other buyers, and brought an extra 48 megawatts of air-cooled capacity online in the first quarter of 2024. The containers sit close together, so the team reworked the evaporative cooling and the way hot exhaust leaves the site.

Kulyk put the bargain in context: built capacity, he said, was then changing hands at 300 to 500 thousand dollars a megawatt.

An 800 megawatt connection

The bigger asset is the grid connection. Storms said Galaxy holds firm approval from ERCOT for 800 megawatts at its project substation. Another 300 megawatts was scheduled for July 2025 and the last 300 for the first quarter of 2027, and the firm paid for the whole substation expansion at the start of 2024.

High-voltage equipment is what slows a project like this, he said. Long-lead items take 18 to 36 months, depending on the voltage of the connection. Sites tied in at 138 kV move faster but get far less capacity. Helios needed transformers and 345 kV breakers, and Storms found a way to move up the line for both.

I legitimately just bought slots from hydrogen, big hydrogen projects, green hydrogen projects that failed to get permanent financing for their build outs.

Austin Storms · 12:24

Everything downstream of that is roughly a nine month build time.

Austin Storms · 12:42

The substation, in other words, sets the calendar. Once the high-voltage gear is in place, he said, hundreds of megawatts of medium and low voltage plant can follow within about a year.

AI, HPC and the value of an electron

Kulyk then raised the question every large miner was hearing that summer: what about AI and high-performance computing? Storms said he had answered it more times than he could count in the previous month, and that Galaxy had spent six to eight months studying the infrastructure side of both. The two are not the same, he noted, in how the building must be designed or in the data center tier an operator can offer. He likes Bitcoin mining, and Galaxy is a crypto-native firm. That, he said, is not the test.

my job is to maximize the value of the electron as it flows through my substation

Austin Storms · 8:17

Larger companies had already approached the firm. Storms judged the market to be early, short of a real scramble for power, and he was content to wait.

I'm happy to be sitting on the 800 megawatt interconnect

Austin Storms · 8:34

Time has borne that out. Galaxy has since leased Helios capacity to the AI cloud company CoreWeave, and the campus is being converted from a Bitcoin mine into an AI data center.

A spin-out, a team and a swimming pool

Asked whether Helios might one day be spun out as its own public company, Storms said Galaxy had looked at every option. He pointed to regulatory uncertainty, and he acknowledged what sell-side analysts tell him: inside a larger firm, the mining business is valued at a conglomerate discount. For now Galaxy is keeping its options open through a stretch of very low hashprice after the halving. The interest from outside, he admitted, now takes up much of his day.

I spend more time today on that piece of the business than I do on the engineering and operations.

Austin Storms · 10:30

He can afford to, he said, because he and a colleague spent about 18 months hiring strong people and then staying out of their way. Most of the site crew lives in Spur, Texas, where Galaxy had just finished a community pool it took on as an obligation of the purchase. It opened on Memorial Day.

It was the most expensive pool I've ever built in my entire life.

Austin Storms · 6:51

Bitcoin traded near $61,272 when the session was recorded and near $82,531 on October 16, 2026.

This story and many more play 24/7 on Bitcoin Radio.

Be in the room next time.

The power is on this floor. Be in the room.

March 22–24, 2027 · Irving Convention Center · Dallas

Intelligence Disrupt 2027Dallas · Mar 22–24Passes from $199Get tickets