PUE and how much power data centers use
PUE, power usage effectiveness, is a data center's total energy divided by the energy its IT equipment uses, measured over a year. A PUE of 1.0 would mean every kilowatt-hour goes to computing; the industry average was 1.52 in Uptime Institute's 2026 survey, while Google reports 1.09 across its fleet. US data centers used 176 TWh in 2023, about 4.4% of the country's electricity, and could reach 6.7% to 12% by 2028. This guide explains the metric, the benchmarks and the numbers behind data center power use.
Published November 20, 2026.
What PUE is
Power usage effectiveness compares everything a data center draws with what reaches the computers. The rest goes to cooling, power conversion losses, lighting and other overhead. The Green Grid published the metric in 2007 and it is now the international standard ISO/IEC 30134-2. Its inverse, DCiE, expresses the same thing as a percentage.
How to calculate PUE
- PUE = total facility energy ÷ IT equipment energy, both in kWh over a full year.
- Example: a site uses 10,000 MWh in a year and its IT equipment uses 8,000 MWh. PUE = 10,000 ÷ 8,000 = 1.25, so each kWh of computing carries 0.25 kWh of overhead. DCiE = 80%.
- Where you measure matters: at the UPS output (level 1), the PDU output (level 2) or the IT equipment itself (level 3, at least every 15 minutes).
Industry average PUE
| Year | Average PUE (Uptime Institute) |
|---|---|
| 2007 | 2.50 |
| 2011 | 1.98 |
| 2014 | 1.65 |
| 2018 | 1.58 |
| 2020 | 1.59 |
| 2022 | 1.55 |
| 2024 | 1.56 |
| 2025 | 1.54 |
| 2026 | 1.52 |
Uptime describes seven years of near standstill: older sites dominate the average, while respondents' largest sites averaged about 1.45 in 2026. Average rack density rose above 11 kW in 2026, and 24% of respondents now run racks of 30 kW or more.
PUE at Google, Meta, Microsoft and AWS
| Operator | PUE | Year |
|---|---|---|
| Google (fleet) | 1.09 | 2025 |
| Meta | 1.08 | 2024 |
| AWS (global) | 1.14 | 2025 |
| Microsoft (fleet) | 1.17 | FY2025 |
Hyperscalers reach these figures with large, purpose-built sites, outside-air and liquid cooling, and high utilization. Liquid-cooled AI racks change the picture again: see liquid cooling and GPU power and cooling.
How much power data centers use
| Measure | Figure | Source |
|---|---|---|
| US data centers, 2014 | 58 TWh | DOE / LBNL |
| US data centers, 2023 | 176 TWh, about 4.4% of US electricity | DOE / LBNL |
| US data centers, 2028 projection | 325–580 TWh, 6.7–12% | DOE / LBNL |
| World, 2024 | About 415 TWh, about 1.5% of electricity | IEA |
| World, 2025 | About 485 TWh (+17%) | IEA |
| World, 2030 projection | About 950 TWh, about 3% | IEA |
The IEA attributes 45% of 2024 data center use to the US, 25% to China and 15% to Europe, and says AI-focused data centers' use grew 50% in 2025.
How big a data center is
| Type | Typical power |
|---|---|
| Enterprise colocation requirement | 500 kW–3 MW per user (JLL) |
| Conventional data center | 10–25 MW (IEA) |
| Hyperscale or AI data center | 100 MW or more (IEA) |
| Largest campuses under construction | About 2 GW (IEA) |
See the largest data centers in the world, and what it costs to build one in data center cost per MW.
WUE: the water metric
Water usage effectiveness is the liters of water used for cooling and humidification per kWh of IT energy. Reported figures: AWS 0.12, Meta 0.19 and Microsoft 0.27 L/kWh. Closed-loop liquid cooling, as at Microsoft's Fairwater sites, avoids evaporating water.
Power producers, cooling vendors and operators meet at Intelligence Disrupt 2027 in Dallas, March 22–24.
Questions
- What is PUE?
- Total facility energy divided by IT equipment energy over a year. The Green Grid introduced it in 2007, and it is standardized as ISO/IEC 30134-2.
- What is a good PUE?
- 1.0 is the theoretical ideal. The industry average was 1.52 in 2026 according to Uptime Institute, large sites averaged about 1.45, and the hyperscalers report 1.08 to 1.17.
- How do you calculate PUE?
- Divide the facility's total annual energy by the IT equipment's annual energy. A site that uses 10,000 MWh while its IT uses 8,000 MWh has a PUE of 1.25.
- What PUE does Google have?
- Google reports a fleet-wide trailing twelve-month PUE of 1.09 for 2025 and the second quarter of 2026.
- How much electricity do US data centers use?
- 176 TWh in 2023, about 4.4% of US electricity, according to Lawrence Berkeley National Laboratory, which projects 325 to 580 TWh, 6.7% to 12%, by 2028.
- How much electricity do data centers use worldwide?
- About 415 TWh in 2024 and about 485 TWh in 2025, according to the IEA, which projects about 950 TWh by 2030, around 3% of global electricity demand.
- How much power does one data center use?
- Conventional data centers run 10 to 25 MW, hyperscale and AI data centers 100 MW or more, and the largest campuses under construction about 2 GW, according to the IEA.
- What is WUE?
- Water usage effectiveness: liters of water used for cooling per kWh of IT energy. AWS reports 0.12, Meta 0.19 and Microsoft 0.27.
More guides
- AI data centers: what they are, how they work and what they cost
- GPU cloud: providers, prices and the power behind them
- Liquid cooling for data centers
- Data center power: how much it takes and how to get it
- Bitcoin miners turning into AI and HPC data centers
- Texas data centers: Dallas-Fort Worth and the AI campuses
- Stargate: every OpenAI data center site and where it stands
- NVIDIA GPU power and cooling requirements
- The largest data centers in the world
- How much does it cost to build a data center?
Sources
- The Green Grid, PUE: a comprehensive examination of the metric (WP49) · 2012
- ISO/IEC 30134-2, Power usage effectiveness · 2016
- Uptime Institute, Global Data Center Survey 2025 · 2025-07
- Uptime Institute, Global Data Center Survey 2026 · 2026-07
- Google, data center efficiency · 2026
- Meta, 2025 Environmental Data Index · 2025
- Microsoft, datacenter efficiency · 2026-03-10
- Amazon, AWS cloud sustainability · 2026
- US DOE, LBNL data center energy report · 2024-12-20
- IEA, Energy and AI · 2025
- IEA, Key questions on energy and AI · 2026
The power is on this floor. Be in the room.
March 22–24, 2027 · Irving Convention Center · Dallas
Intelligence Disrupt and Mining Disrupt are NOT affiliated with any other brands, groups, events, meetups, individuals, sponsors, exhibitors, agents, or referrals, except the Industry Ambassadors listed on this site. We do not sell any lists. Beware of scams claiming otherwise.
There are imitators and scammers using our name to solicit sponsors and attendees. Always verify directly through our official Telegram group. Stay vigilant!
Intelligence Disrupt Policy: No refunds. No outside food or drinks. No third-party event solicitations.
Unauthorized solicitation, sales, advertising, product demonstrations, or distribution of promotional materials, including magazines, brochures, flyers, catalogs, business literature, and promotional giveaways, is strictly prohibited anywhere within the event venue unless expressly authorized by Intelligence Disrupt.
Marketing activities are reserved exclusively for approved exhibitors, sponsors, and authorized event partners. Attendees found engaging in unauthorized promotional activities may be required to cease immediately, surrender promotional materials, and may have their event credentials revoked without refund at the sole discretion of event management.