Texas data centers: Dallas-Fort Worth and the AI campuses
Texas is where much of the US AI build-out is happening. Dallas-Fort Worth is one of the country's largest data center markets, and West Texas hosts several gigawatt-scale AI campuses, including OpenAI's Stargate site in Abilene. This page lists the major campuses with the owner, the announced capacity and the status, each taken from the company's own announcement, and explains how ERCOT connects them to the grid.
Published November 20, 2026. Status is as announced by each owner on the date shown; where a figure is not published we say so.
Dallas-Fort Worth data centers
Dallas-Fort Worth is the established market: hyperscaler and colocation campuses clustered south of Dallas in Ellis County and around Fort Worth, with fiber and power already in place. Intelligence Disrupt 2027 takes place in Irving, between the two cities.
| Campus | City | Owner | Announced capacity | Status |
|---|---|---|---|---|
| Google Midlothian | Midlothian | Not published | Operating | |
| Google Red Oak | Red Oak | Not published | Operating | |
| DataBank Red Oak | Red Oak | DataBank | 240 MW IT in phase 1, 480 MW at full build | Under construction; first service targeted Q2 2026 |
| Compass Red Oak | Red Oak | Compass Datacenters | 350+ MW IT planned | Built in phases |
| CyrusOne DFW7 | Fort Worth | CyrusOne with Eolian | 200 MW | Under construction; delivery from 2026 |
| QTS Fort Worth 1 | Fort Worth | QTS | 70+ MW critical, 200 MW gross planned | Operating |
| Meta Fort Worth | Fort Worth | Meta | Not published | Operating |
| Denton HPC site | Denton | Core Scientific (tenant CoreWeave) | Just over 260 MW critical IT | Operating and expanding |
AI campuses across Texas
The gigawatt-scale AI campuses are mostly in West Texas, where land and power are easier to secure. Several were Bitcoin mining sites first: Galaxy's Helios, IREN's Childress and Cipher's Barber Lake now host AI tenants.
| Campus | Location | Owner / partners | Announced capacity | Status |
|---|---|---|---|---|
| Stargate Abilene | Abilene | Crusoe, Oracle, OpenAI | About 1.2 GW, 8 buildings | 2 buildings operating, 6 under construction |
| Crusoe campus for Microsoft | Abilene | Crusoe, Microsoft | 900 MW | Site work; first building expected mid-2027 |
| Frontier | Shackelford County | Vantage (Oracle, OpenAI) | 1.4 GW, 10 buildings | Under construction; first building due H2 2026 |
| Stargate Milam County | Milam County | SB Energy (SoftBank), leased to OpenAI | 1.2 GW | Under construction |
| Meta El Paso | El Paso | Meta | 1 GW | Under construction |
| Meta Temple | Temple | Meta | Not published | Operating since July 2026 |
| Helios | West Texas | Galaxy (tenant CoreWeave) | 1.6+ GW ERCOT-approved | Phase I (133 MW IT) delivered; Phase II under construction |
| IREN Childress | Childress | IREN (customer Microsoft) | 750 MW campus | Phased rollout through 2026 |
| Project Horizon | West Texas | Poolside, CoreWeave | 2 GW; first phase 250 MW | Announced |
| Barber Lake | Colorado City | Cipher (tenant Fluidstack) | 168 MW IT, up to 244 MW gross | Delivery expected by Sept 2026 |
| GW Ranch | Pecos County | Pacifico Energy | 7.65 GW gas generation permitted | Phase 1 power expected H1 2027 |
| Project Matador | Near Amarillo | Fermi | About 17 GW planned | Pre-revenue; no binding lease yet |
| Google Armstrong and Haskell counties | Panhandle and Haskell County | Not published | Announced (part of $40B in Texas) |
For the full list of OpenAI sites in Texas and elsewhere, see the Stargate site tracker.
How ERCOT connects data centers
- The queue is huge. About 474 GW of large loads were seeking to connect as of June 2026, about 90% of them data centers, according to ERCOT.
- Batch studies replaced one-by-one studies. The old process ended July 10, 2026. Loads of 75 MW or more moved into a one-time Batch Zero study; in September 2026 ERCOT provisionally kept 362 loads and excluded 302 GW.
- New connections are paused. After Governor Abbott ordered a verification and audit on August 3, 2026, ERCOT paused the study and stopped approving energization of data center and crypto loads of 75 MW or more. Loads of 25 to 75 MW are not affected.
- What comes next. Final Batch Zero decisions are expected in December 2026, and later batches will run about every six months.
What SB 6 requires
- A screening study fee of at least $100,000 for loads of 75 MW or more.
- Proof of site control and a financial commitment set by the PUCT.
- Disclosure of duplicate requests elsewhere in Texas and of on-site backup generation.
- Loads connected at transmission voltage after December 31, 2025 must be curtailable during firm load shed.
- ERCOT buys demand reductions from large loads and can order backup generation in emergencies.
Why Texas
Power, land and a grid market that rewards flexible load. Bitcoin miners proved the model first: they connected large loads in ERCOT and earned money by switching off at peak. AI operators now buy or lease the same powered sites. For the power side, read the data center power guide; for the buildings, the AI data center guide.
The companies building these campuses meet in Dallas at Intelligence Disrupt 2027, March 22–24, on the same floor as Mining Disrupt.
Questions
- How many data centers are in Texas?
- There is no official count. Dallas-Fort Worth alone hosts campuses from Google, Meta, QTS, CyrusOne, DataBank and Compass, and the AI campuses announced across the state since 2025 add several gigawatts, led by Abilene, Shackelford County, Milam County and El Paso.
- Where are the data centers in Dallas-Fort Worth?
- Mostly south and west of Dallas and around Fort Worth: Google in Midlothian and Red Oak, DataBank and Compass in Red Oak, CyrusOne, QTS and Meta in Fort Worth, and Core Scientific's CoreWeave site in Denton.
- What is the largest data center in Texas?
- By announced capacity, the largest campuses are the AI sites: Vantage's Frontier campus in Shackelford County (1.4 GW), Crusoe's Stargate campus in Abilene (about 1.2 GW), SB Energy's Milam County site (1.2 GW) and Meta's El Paso campus (1 GW). Fermi plans about 17 GW near Amarillo but has no binding customer yet.
- Why are so many AI data centers being built in Texas?
- Land, a fast-growing power supply and the ERCOT market, which lets large flexible loads connect and be paid to cut demand. Texas also allows on-site gas generation, which several AI campuses use.
- Can a new data center connect to ERCOT right now?
- Not quickly. ERCOT moved loads of 75 MW or more into a batch study in July 2026, and after the governor ordered an audit on August 3, 2026, it paused energization of new data center and crypto loads of 75 MW or more until the audit is done. Loads of 25 to 75 MW are not affected.
- How big is ERCOT's large-load queue?
- ERCOT reported about 474 GW of large loads seeking to connect as of June 2026, about 90% of them data centers. Its September 2026 Batch Zero screening provisionally kept 362 loads and excluded 302 GW.
- What does Texas SB 6 change for data centers?
- SB 6 (2025) sets standards for loads of 75 MW or more: a screening study fee of at least $100,000, proof of site control, a financial commitment, disclosure of duplicate requests and backup generation, and curtailment during firm load shed for loads connected after December 31, 2025.
More guides
- AI data centers: what they are, how they work and what they cost
- GPU cloud: providers, prices and the power behind them
- Liquid cooling for data centers
- Data center power: how much it takes and how to get it
- Bitcoin miners turning into AI and HPC data centers
- Stargate: every OpenAI data center site and where it stands
- NVIDIA GPU power and cooling requirements
- The largest data centers in the world
- How much does it cost to build a data center?
- PUE and how much power data centers use
Sources
- Google, Ellis County data center · 2026-11
- DataBank, Red Oak campus construction · 2025-11-10
- Compass Datacenters, second Dallas-area campus · 2020-01-29
- CyrusOne and Eolian, 200 MW Fort Worth campus · 2026-01-13
- QTS, Fort Worth data center · 2026-11
- Meta, Fort Worth data center · 2015-07-07
- Core Scientific and CoreWeave, Denton (SEC exhibit) · 2025-02-26
- Crusoe, contracted capacity approaches 5 GW · 2026-06-09
- Crusoe, 900 MW Abilene campus for Microsoft · 2026-03-27
- Vantage Data Centers, Frontier campus · 2025-08-19
- OpenAI, Stargate and SB Energy · 2026-01-09
- Fermi, results release (SEC exhibit) · 2026-11-12
- Google, $40 billion in Texas · 2025-11-14
- Google, Meitner Energy Center · 2026-06-04
- Meta, El Paso AI data center · 2026-03-26
- DCD, Meta starts operations in Temple · 2026-07
- Galaxy, ERCOT approval for additional 830 MW · 2026-01-15
- Galaxy, Helios Phase I complete · 2026-07-06
- IREN, $9.7 billion contract with Microsoft · 2025-11-03
- CoreWeave and Poolside, Project Horizon · 2025-10-15
- Pacifico Energy, GW Ranch air permit · 2026-01-26
- Cipher, 168 MW AI hosting agreement · 2025-09-25
- ERCOT, large load update to the Texas Senate · 2026-07-29
- ERCOT, Batch Zero update · 2026-09-11
- ERCOT, Batch Zero verification and audit (PUCT) · 2026-08-20
- Texas Legislature, SB 6 bill analysis · 2025
The power is on this floor. Be in the room.
March 22–24, 2027 · Irving Convention Center · Dallas
Intelligence Disrupt and Mining Disrupt are NOT affiliated with any other brands, groups, events, meetups, individuals, sponsors, exhibitors, agents, or referrals, except the Industry Ambassadors listed on this site. We do not sell any lists. Beware of scams claiming otherwise.
There are imitators and scammers using our name to solicit sponsors and attendees. Always verify directly through our official Telegram group. Stay vigilant!
Intelligence Disrupt Policy: No refunds. No outside food or drinks. No third-party event solicitations.
Unauthorized solicitation, sales, advertising, product demonstrations, or distribution of promotional materials, including magazines, brochures, flyers, catalogs, business literature, and promotional giveaways, is strictly prohibited anywhere within the event venue unless expressly authorized by Intelligence Disrupt.
Marketing activities are reserved exclusively for approved exhibitors, sponsors, and authorized event partners. Attendees found engaging in unauthorized promotional activities may be required to cease immediately, surrender promotional materials, and may have their event credentials revoked without refund at the sole discretion of event management.